Deckers Germany
One of the biggest growers decided to build a new facility from scratch near the market of Frankfurt. Christiaens was given the order to build 22 growing rooms of 820m2 completely turnkey. The project was split into 2 phase to be able to have mushrooms before Christmas and to start-up the project in 2 steps. The first stage was 14 rooms. In November 2014 the first rooms were filled. The second stage of 8 growing rooms will be ready in the summer of 2015.
Drawer System
Modern mushroom cultivation knows serious challenges. In the area of personnel, for...
Lees meerChristiaens Group takes over Hedonk activities
As of 1 May, Christiaens Group BV has acquired the majority of Hedonk's...
Lees meerSolar Panels
Christiaens group invested in 4146 solar panels. We not only save on energy costs,...
Lees meerTILTING SHELVES
Increase substantial harvesting efficiencies Good ergonomics Extendable with...
Lees meer